New PRM Meeting Point, T5 Level 3
- Status
- Active
- Sequence number:
- AI-498-2026
- Category:
- General
- Location:
- Landside
- From:
- To:
- Affected airports:
- Stockholm Arlanda Airport
What is happening or what needs to be done?
A new PRM Meeting Point is established on T5 floor 3. The work includes assembly of wooden structure (rim incl ribs), suspended U-roof, electrical installations, lighting, signage, FIDS.
Consequences? Who is particularly affected?
Temporary disturbances may occur in connection with construction and installation work, but are considered to be manageable through planning and coordination.
Which area of the airport is affected?
Terminal 5 (T5), level 3 landside.
For further information
Client - Swedavia:
Project leader: Danijel Petrovic, danijel.petrovic@swedavia.se, 010-109 05 39
Contractor: Dantent, Mats Hverén, Mats@dandent.se, 070-575 10 10
Contractor: Emil Lundgren, Robert Niord, robert.niord@emillundgren.se, 0723-898151