Filling the hydrant ramp BC
- Sequence number:
- AI-499-2026
- Category:
- General
- Location:
- Airside
- From:
- To:
- Affected airports:
- Stockholm Arlanda Airport
What is happening or what needs to be done?
Filling of the hydrant will take place for ramp BC. We will work our way from staging 20 to 43. And we will go down into chambers for work and aeration of the system will take place at all outlet posts. And also the aeration post at Skycity on the city road.
Consequences? Who is particularly affected?
Parking space 20 will continue to be closed and work will take place within the closure. Vehicles will be parked in connection with work at 07.00.
Seat 43 will be closed from 12:00 noon and the area of the hydrant chamber will be closed.
Within ramp BC, tanker trucks and cars will travel to access chambers and aeration posts.
On the city road outside Skycity, there will be a lane closed for about 1 hour during the day when the line is ventilated on that stretch. See picture TA plan.
Which area of the airport is affected?
Places 20 and 43 as well as ramp BC and the city road at Skycity.
For further information
Tomas Stenbäck, Construction Manager Swedavia AB, 070-6930412, tomas.stenback@swedavia.se
Erik Pernler, BAS-U, Swedavia AB, 070-1674719, erik.pernler@swedavia.se
Ryan Strömberg, SVEAB, 070-4587683, ryan.stromberg@sveab.se
Jonas Karlsson, AFAB, 070-7253208, jonas.karlsson@flygbranslehantering.se
Published Latest change