  1. Planned power outage Terminal 4 busbar B and D

Planned power outage Terminal 4 busbar B and D

Sequence number:
AI-418-2026
Category:
General
Location:
Airside, Landside
From:
2026-10-21 23:00
To:
2026-10-22 04:00
Affected airports:
Stockholm Arlanda Airport

What is happening or what needs to be done?

Duct rails B and D will be moved to a new switchgear. There will be interruptions in power supply for everything connected to these busbars during the time of the work. 

Consequences? Who is particularly affected?

See picture below for the approximate area that is affected (red and blue marking). If you have a power outlet with a designation that starts with B or D, you can also infer if there will be an impact.

UPS power and diesel genset backup power are not affected and these will be operational.

Which area of the airport is affected?

Terminal 4 

Yta som påverkas av strömavbrott i Terminal 4 markerad i färg

For further information

Project Manager Swedavia, Tim Sidemark, tim.sidemark@swedavia.se , 0724 02 66 85
CAM coordinator: Christer Lindwall. Phone: 010-109 15 09
CAM coordinator: Sam Karlsson. Phone: 010-109 41 21

Published Thursday, October 8, 2026 Latest change Thursday, October 8, 2026