Maintenance work Sky City
- Status
- Active
- Sequence number:
- AI-257-2026
- Category:
- General
- Location:
- Landside
- From:
- To:
- Affected airports:
- Stockholm Arlanda Airport
What is happening or what needs to be done?
Maintenance work will be carried out in the Sky City building due to moisture ingress into the frame.
The work includes:
- Replacement of waterproofing on the outside around certain steel columns
- Replacement of waterproofing inside floor drains and loading bays
- Rust and fire protection painting of internal beams and columns
- Cleaning of floor drains
- Painting work of walls and steel structures
Start 2026-08-10 in the parking garage floor 0-2
Start 2026-08-23 ground floor outside Sky City
End 2026-10-30
Consequences? Who is particularly affected?
Impact on travelers: Rerouting of walkways according to traffic guidance.
Impact on operation: Relocation of bus lanes according to traffic guidance, closure of parking spaces both inside and outside.
Which area of the airport is affected?
Building (901) Sky City from floor 0-2
For further information
Contact person contractor:
Ryan Strömberg (Sveab), 070-458 76 83
Contact project management Swedavia:
BAS-P: Michael Persson 072-201 68 57
BAS-U: Niklas Zetterberg 070-605 02 04
Project leader: Shamil Iskhadzhiev 076-721 39 96
Construction Manager: Gustav Litsfeldt 072-212 04 74
CAM Coordinator Charlotta Bengtsson 0708-916114
Case number: STO-2026-094
Published