Skip to content
Swedavia extranet, to the start page.
Byt språk till Svenska
  1. Paving work at T11

Paving work at T11

Sequence number:
AI-201-2026
Category:
Traffic
Location:
Airside
From:
2026-06-14 22:00
To:
2026-06-16 05:00
Affected airports:
Stockholm Arlanda Airport

What is happening or what needs to be done?

Milling and asphalting on part of Cityvägen at T11.

The passage under pier B will be closed during the current period.

Consequences? Who is particularly affected?

Buses operating on the T11.

Which area of the airport is affected?

Cityvägen -in front of T11/ 11X

TA-plan som visar avstängningen av genomfarten under pir B

For further information

Swedavia:
Erik Pernler, Mob: 070-167 47 19
André Lindström, Mob: 070-291 47 97

Contractor:
Jesper Schwartz Sveab, Mob: 073-347 58 73
Dan Sjöman Svevia, Mob: 070-205 50 80

Published Tuesday, June 9, 2026

Swedavia extranet, logotype.

Emergency

112

Police

114 14

Customs office

90 114

©Copyright 2026 Swedavia