Moving the blastfence on apron F-A
- Sequence number:
- AI-187-2026
- Category:
- General
- Location:
- Airside
- From:
- To:
- Affected airports:
- Stockholm Arlanda Airport
What is happening or what needs to be done?
- The blastfence between A and F piers will be moved north to create a temporary parking lot for battery-powered luggage trucks, and the blastfence will be moved 4 meters forward for about 40 meters as shown in the picture below. The area will be cordoned off with a heavy barrier to the road. The trucks will drive in and park diagonally against the blast fence. The move is simulated and no new push routines will be needed.
- After the move, charging boxes will be installed. Electricity supply to these will be routed via a portal over the road, which will be installed on Friday night starting at 23:00 Thursday evening
Consequences? Who is particularly affected?
The work on the portal means that one lane at a time past the work area will be closed.
Which area of the airport is affected?
Apron between A and F pir
For further information
Construction Manager Swedavia: Peter Eriksson, 070-388 56 57
Contractor Rosersberg: Pelle Smeds, 070-655 84 03
CAM case STO-2026-069
CAM coordinator, Christer Lindwall. Tel; 010-109 15 09
CAM coordinator, Sam Karlsson. Tel; 010-109 41 21